Power Down the Node
This chapter explains how to power down a node and stop all node activity on the Cisco ONS 15454.
NTP-A114 Power Down the Node
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Do not reach into a vacant slot or chassis while you install or remove a module or a fan. Exposed
Warning
circuitry could constitute an energy hazard. Statement 206
The following procedure is designed to minimize traffic outages when powering down nodes, but traffic
Caution
will be lost if you delete and recreate circuits that passed through a working node.
Always use the supplied ESD wristband when working with the Cisco ONS 15454. Plug the wristband
Note
into the ESD jack located on the fan-tray assembly or on the lower right outside edge of the shelf on the
NEBS 3 shelf assembly. To access the ESD plug on the NEBS 3 shelf assembly, open the front door of
the Cisco ONS 15454. The front door is grounded to prevent electrical shock.
Identify the node that you want to power down. If no cards are installed, go to Step 13. If cards are
Step 1
installed, log into the node. See the
Step 2
In node view, choose Go to Network View from the View menu.
December 2004
This procedure stops all node activity.
None
None
As needed
Onsite
For software steps, provisioning level or higher is required.
For hardware steps, any level is allowed.
"DLP-A60 Log into CTC" task on page 17-66
C H A P T E R
for instructions.
Cisco ONS 15454 Procedure Guide, R5.0