Cisco ONS 15454 Series Procedure Manual page 164

Hide thumbs Also See for ONS 15454 Series:
Table of Contents

Advertisement

NTP-A48 Subtend a BLSR from a BLSR
Stop. You have completed this procedure.
NTP-A48 Subtend a BLSR from a BLSR
Purpose
Tools/Equipment
Prerequisite Procedures None
Required/As Needed
Onsite/Remote
Security Level
This procedure assumes that all nodes are configured for the BLSR. If you need to add a node to a BLSR,
Note
see the
Step 1
Complete the
(Node 4 in
Step 2
Install the OC-N cards that will serve as the BLSR trunk (span) cards if they are not already installed.
See the
Figure 5-13
runs on Nodes 4, 5, 6, and 7 and represents the subtending ring added by this procedure. Two BLSR
rings, Ring 1 and Ring 2, are provisioned on Node 4. Ring 1 uses cards in Slots 5 and 12, and Ring 2
uses cards in Slots 6 and 13.
Cisco ONS 15454 Procedure Guide, R5.0
5-38
This procedure subtends a BLSR from an existing BLSR.
One BLSR node must have OC-N cards and fibers needed to carry the
second BLSR.
As needed
Onsite
Provisioning and higher
"NTP-A212 Add a BLSR Node" procedure on page
"DLP-A60 Log into CTC" task on page 17-66
Figure
5-13). If you are already logged in, continue with Step 2.
"NTP-A16 Install the OC-N Cards" procedure on page
shows two BLSRs shared by one ONS 15454. Ring 1 runs on Nodes 1, 2, 3, and 4. Ring 2
Chapter 5
14-2.
at the node that will subtend the BLSR
2-6.
Turn Up Network
December 2004