DLP-A29 Route DS-1 and DS-3/EC-1 Twisted-Pair Cables
Figure 17-17
Tie-wrap
Return to your originating procedure (NTP).
Step 4
DLP-A29 Route DS-1 and DS-3/EC-1 Twisted-Pair Cables
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Verify the following:
Step 1
Tie-wrap or lace the DS-1 and DS-3/EC-1 twisted-pair cables according to local site practice and route
Step 2
the cables into the side cutouts on either side of the ONS 15454.
Cisco ONS 15454 Procedure Guide, R5.0
17-36
Routing Coaxial Cable (SMB EIA Backplane)
Connector ends
B
posts
Tie-wraps
This task routes the DS-1 and DS-3/EC-1 twisted-pair cables.
None
DLP-A23 Install DS-1 Cables Using Electrical Interface Adapters (Balun),
page 17-28
As needed
Onsite
None
DS-1 electrical interface adapters are installed on every transmit and receive connector for DS-1
ports.
Wire-wrap posts on the DS-1 electrical interface adapters are used to connect the terminated
incoming cables.