As needed, install a tie-bar or other strain-relief device, according to local site practice.
Figure 16-12
Figure 16-12
Cisco ONS 15310-MA SDH Procedure Guide, Release 9.1 and Release 9.2
16-18
This task routes electrical, optical, alarm, and timing cables away from the
ONS 15310-MA SDH. You can install optional tie-bars specifically
designed for the ONS 15310-MA SDH.
Tie-wraps or other securing devices, according to local practice
Tie-bar(s) (15310-TIE-BAR-19; 15310-TIE-BAR-23)
NTP-H158 Install the Electrical Cables, page 1-27
NTP-H160 Install Optical Cables, page 1-29
NTP-H157 Install Wires to Alarm, Timing, Craft, LAN, and UDC Pin
Connections, page 1-26
As needed
Onsite
None
shows how to install a tie-bar on an ONS 15310-MA SDH rack.