Cisco ONS 15454 Install
Cisco ONS 15454 Install

Cisco ONS 15454 Install

Install the shelf and backplane cable
Hide thumbs Also See for ONS 15454:

Advertisement

Quick Links

Install the Shelf and Backplane Cable
This chapter provides procedures for installing the Cisco ONS 15454. For a summary of the tools and
equipment required for installation, see the
Before You Begin
This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
78-18537-01
before continuing with the
assembly in a rack.
equipment before continuing with other procedures.
backplane before continuing with other procedures.
This procedure is a prerequisite to the
1-22.
the
"NTP-A7 Install the Fan-Tray Assembly" procedure on page
assembly in the shelf.
planning to install the Alarm Interface Controller-International (AIC-I) card and want to increase
the number of alarm contacts provided by the AIC-I card.
this procedure as needed to set up wire-wrap pin connections.
connect an external wire-wrap panel to the alarm expansion panel (AEP).
NTP-A9 Install the Electrical Card Cables on the Backplane, page
if you plan to install electrical card cables.
NTP-A10 Route Electrical Cables, page
electrical cables installed on the backplane.
C H A P T E R
"Required Tools and Equipment" section on page
"NTP-A2 Install the Shelf Assembly" procedure on page
1-5-Complete this procedure to install the shelf
1-6-Complete this procedure to access the
1-7-Complete this procedure to access the
1-8-Complete this procedure if you plan to install electrical cards.
"NTP-A9 Install the Electrical Card Cables on the Backplane"
1-9-Complete this procedure before continuing with
1-11-Complete this procedure to install the fan-tray
1-13-Complete this procedure if you are
1-23-Complete this procedure as needed to route
Cisco ONS 15454 Procedure Guide, Release 8.5.1
1
1-2.
1-4-Complete this procedure
1-5.
1-11.
1-16-Complete
1-17-Complete this procedure to
1-22-Complete this procedure
1-1

Advertisement

Table of Contents
loading

Summary of Contents for Cisco ONS 15454

  • Page 1: Table Of Contents

    C H A P T E R Install the Shelf and Backplane Cable This chapter provides procedures for installing the Cisco ONS 15454. For a summary of the tools and equipment required for installation, see the “Required Tools and Equipment” section on page 1-2.
  • Page 2 You need the following tools and equipment to install and test the ONS 15454. Cisco-Supplied Materials The following materials are required and are shipped with the ONS 15454 shelf (wrapped in plastic). The number in parentheses gives the quantity of the item included in the package.
  • Page 3 Mounting brackets, 19 inch (482.6 mm), 23 inch (584.2 mm) (2) • User-Supplied Materials The following materials and tools are required but are not supplied with the ONS 15454: One or more of the following equipment racks: • 19-inch ANSI Standard (Telcordia GR-63-CORE) (482.6 mm) rack; total width 22 inches –...
  • Page 4: Ntp-A1 Unpack And Inspect The Ons 15454 Shelf Assembly, Page

    Required Onsite/Remote Onsite Security Level None The ONS 15454 high-density shelf (15454-SA-HD) is required if you want to use the high-density Note electrical cards (DS3/EC1-48 and DS1/E1-56 cards). Complete the “DLP-A1 Unpack and Verify the Shelf Assembly” task on page 17-1.
  • Page 5: Ntp-A2 Install The Shelf Assembly, Page

    Warning The ONS 15454 must have 1 inch (25.4 mm) of airspace below the installed shelf assembly to allow air flow to the fan intake. The air ramp (the angled piece of sheet metal on top of the shelf assembly) provides this spacing and should not be modified in any way.
  • Page 6: Ntp-A3 Open And Remove The Front Door, Page

    NTP- A3 Open and Remove the Front Door The 10-Gbps-compatible shelf assembly (15454-SA-HD) and fan-tray assembly (15454-FTA3) are Note required with the ONS 15454 XC10G, OC-192, and OC-48 any slot (AS) cards. The ONS 15454 installations are suitable for Network Telecommunication facilities and locations where Note NEC are applicable.
  • Page 7: Ntp-A4 Remove The Backplane Covers, Page

    If you plan to install electrical interface assemblies (EIAs), continue with the “NTP-A5 Install the EIAs” procedure on page 1-8. If not, continue with the “NTP-A6 Install the Power and Ground” procedure on page 1-9. Stop. You have completed this procedure. Cisco ONS 15454 Procedure Guide, Release 8.5.1 78-18537-01...
  • Page 8 Onsite Security Level None Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband Caution cable into the ESD jack located on the lower-right outside edge of the shelf assembly. EIAs are normally factory installed. Verify that the correct EIA is installed on the shelf assembly. If not, Note install the correct EIA.
  • Page 9: Ntp-A6 Install The Power And Ground, Page

    “NTP-A6 Install the Power and Ground” procedure on page 1-9. Stop. You have completed this procedure. NTP-A6 Install the Power and Ground Purpose This procedure installs power feeds and grounds the ONS 15454. Tools/Equipment #2 Phillips screwdriver Medium slot-head screwdriver Small slot-head screwdriver...
  • Page 10 This unit might have more than one power supply connection. All connections must be removed to de-energize the unit. Statement 1028 Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband Caution cable into the ESD jack located on the lower-right outside edge of the shelf assembly.
  • Page 11: Ntp-A7 Install The Fan-Tray Assembly, Page

    Onsite/Remote Onsite Security Level None Do not operate an ONS 15454 without a fan-tray air filter. A fan-tray air filter is mandatory. Caution The 15454-FTA3 fan-tray assembly can only be installed in ONS 15454 Release 3.1 or later shelf Caution assemblies (15454-SA-ANSI, 800-19857;...
  • Page 12 Chapter 1 Install the Shelf and Backplane Cable NTP- A7 Install the Fan-Tray Assembly If you are installing the ONS 15454 in an outside plant cabinet, remove the air filter to provide maximum Note cooling capabilities and to comply with Telcordia GR-487-CORE.
  • Page 13: Ntp-A119 Install The Alarm Expansion Panel, Page

    15454-SA-ANSI or 15454-SA-HD shelf backplane. The AEP provides alarm contacts in addition to the 16 provided by the AIC-I card. Typically, the AEP is preinstalled when ordered with the ONS 15454; however, the AEP can be ordered separately. The AIC-I card must be installed before you can provision the alarm contacts enabled by the AEP.
  • Page 14 Replace Backplane Screws with Standoffs Longer Shorter Attach the remaining two standoffs on either side of the backplane (Figure 1-3). Step 2 Position the AEP board over the standoffs. Step 3 Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-14 78-18537-01...
  • Page 15 AEP and AIC-I signals that each wire carries. Plug the other end of the AEP cable into AEP connector port. The brown pin is on the top. Figure 1-4 AEP Wire-Wrap Connections to Backplane Pins Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-15 78-18537-01...
  • Page 16: Ntp-A8 Attach Wires To Alarm, Timing, Lan, And Craft Pin Connections, Page

    “DLP-A21 Install LAN Wires on the Backplane” task on page 17-28 as needed. LAN wires Step 3 (or the LAN port on the TCC2/TCC2P) are necessary to create an external LAN connection. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-16 78-18537-01...
  • Page 17: Ntp-A120 Install An External Wire-Wrap Panel To The Aep, Page

    Step 4 the EIA/TIA-232 port on the TCC2/TCC2P) are required to access TL1 using the craft interface. Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the Caution wristband cable into the ESD jack located on the lower-right outside edge of the shelf assembly.
  • Page 18 Table 1-2 Alarm Input Pin Assignments AMP Champ Pin Signal Name AMP Champ Pin Signal Name ALARM_IN_1– ALARM_IN_2– ALARM_IN_3– ALARM_IN_4– ALARM_IN_5– ALARM_IN_6– ALARM_IN_7– ALARM_IN_8– ALARM_IN_9– ALARM_IN_10– ALARM_IN_11– ALARM_IN_12– ALARM_IN_13– ALARM_IN_14– ALARM_IN_15– ALARM_IN_16– Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-18 78-18537-01...
  • Page 19 — NO_1 NO_2 — COM_2 COM_3 — NO_3 NO_4 — COM_4 COM_5 — NO_5 NO_6 — COM_6 COM_7 — NO_7 NO_8 — COM_8 COM_9 — NO_9 NO_10 — COM_10 COM_11 — Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-19 78-18537-01...
  • Page 20 ALARM_IN_21- XREF=6 XREF=6 ALARM_IN_22- ALARM_IN_23- XREF=6 XREF=6 ALARM_IN_24- ALARM_IN_25- XREF=6 XREF=6 ALARM_IN_27- ALARM_IN_26- XREF=6 XREF=6 ALARM_IN_28- ALARM_IN_29- XREF=6 XREF=6 ALARM_IN_31- ALARM_IN_30- XREF=5 ALARM_IN_+ GND2 Figure 1-7 illustrates the alarm output connectors. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-20 78-18537-01...
  • Page 21 Backplane” procedure on page 1-22. If you do not plan to install electrical cards, continue with the “NTP-A11 Install the Rear Cover” • procedure on page 1-23. Stop. You have completed this procedure. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-21 78-18537-01...
  • Page 22 Onsite Security Level None Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband Caution cable into the ESD jack located on the lower-right outside edge of the shelf assembly. Refer to the Cisco ONS 15454 Reference Manual for more information about EIAs.
  • Page 23 You should assemble two extended standoffs for each side, for a total of four extended standoffs per shelf. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-23...
  • Page 24 Figure 1-10 shows the mounting holes on the remaining EIA types (MiniBNC, SMB, etc.). You can identify the mounting holes on all EIAs by locating the REAR COVER BRACKET LOCATION designation. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-24 78-18537-01...
  • Page 25 Chapter 1 Install the Shelf and Backplane Cable NTP- A11 Install the Rear Cover Figure 1-8 Mounting Holes on the UBIC-V EIA B-side A-side mounting mounting holes holes Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-25 78-18537-01...
  • Page 26 Chapter 1 Install the Shelf and Backplane Cable NTP- A11 Install the Rear Cover Figure 1-9 Mounting Holes on the UBIC-H B-side A-side mounting mounting holes holes Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-26 78-18537-01...
  • Page 27 Use a 5/16-inch nutdriver to install the extended standoffs in the mounting holes. Step 4 Locate the TOP designation on one of the mounting bars (700-19701-XX) and align the appropriate Step 5 holes for your EIA with the extended standoffs (Figure 1-11). Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-27 78-18537-01...
  • Page 28 Attach the rear cover (700-06029-XX) by hanging it from the mounting screws on the back of the Step 8 mounting bars and pulling it down until it fits firmly into place (Figure 1-12) or by using standoffs (Figure 1-13). Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-28 78-18537-01...
  • Page 29 Chapter 1 Install the Shelf and Backplane Cable NTP- A11 Install the Rear Cover Figure 1-12 Installing the Rear Cover Onto the Mounting Bars Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-29 78-18537-01...
  • Page 30 The covers are an integral part of the safety design of the product. Do not operate the unit without the Warning covers installed. Step 1 Complete Table 1-5 by verifying that each applicable procedure was completed. Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-30 78-18537-01...
  • Page 31 Shelf Installation Task Summary Description Completed NTP-A1 Unpack and Inspect the ONS 15454 Shelf Assembly, page 1-4 NTP-A2 Install the Shelf Assembly, page 1-5 NTP-A3 Open and Remove the Front Door, page 1-6 NTP-A4 Remove the Backplane Covers, page 1-7...
  • Page 32 Chapter 1 Install the Shelf and Backplane Cable NTP- A13 Perform the Shelf Installation Acceptance Test Cisco ONS 15454 Procedure Guide, Release 8.5.1 1-32 78-18537-01...

Table of Contents