Download Print this page

GE LOGIQ E9 Service Manual page 449

Hide thumbs Also See for LOGIQ E9:

Advertisement

GE H
EALTHCARE
D
5180263-100, R
IRECTION
8-6-8
Lower Operator Panel (OP) replacement
Manpower /
Time
One person /
15 minutes
Table 8-39
Energy Control and Power Lockout for LOGIQ E9
NOTICE
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO VOLTAGE
GREATER THAN 30 VOLTS:
1. TURN OFF THE SCANNER.
2. UNPLUG THE SYSTEM.
3. MAINTAIN CONTROL OF THE SYSTEM POWER PLUG.
TAG
&
LOCKOUT
4. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE AS THERE ARE NO
Signed
Date
TEST POINTS TO VERIFY ISOLATION. THE AMBER LIGHT ON THE OP PANEL ON/OFF
BUTTON WILL TURN OFF.
5. DISCONNECT THE EPS (EXTENDED POWER SHUTDOWN) BATTERY AT J3, OR THE
BATTERY FROM THE CHARGEBOARD AT PCN1 WHEN WORKING IN THE BEP. THIS
SHOULD BE DONE WHENEVER THE BEP IS OPEN AND THE EPS OR CHARGEBOARD IS
EXPOSED AND CHANGING PARTS.
Beware that the Main Power Supply, Extended Power Shutdown or ChargeBoard and BEP may be
energized even if the power is turned OFF if the cord is still plugged into the AC Outlet.
1. Power down the system.
2. Disconnect the mains power cable from the wall outlet and all Probes and External I/O Cabling.
3. Remove Upper OP Panel/Touch Panel Assembly in order to remove the Lower Op Panel.
Preparation Links (if you need more information):
• 4-2-4 "Power shut down" on page 4-7
• 8-6-6 "Upper Operator Panel / Touch Panel Assembly replacement" on page 8-71
5
EV
Table 8-38
Manpower / Time and Tools
• Refer to:
8-2-5 "Tools needed for servicing LOGIQ E9" on page 8-5
• Keytop removal tool
Preparations and Preparation Links
Preparations - you must perform the following steps
Chapter 8 Replacement procedures
LOGIQ E9 Service Manual
Tools
8 - 85

Advertisement

loading