Chapter 4
Turn Up Network
Verify the integrity of all patch cables that will be used in this test by connecting one end to the test set
Step 10
transmit (Tx) connector and the other end to the test set receive (Rx) connector. If the test set does not
run error-free, check the cable for damage and check the test set to make sure it is set up correctly before
continuing.
Step 11
Create a physical loopback at the circuit destination card:
Attach one end of a patch cable to the destination port transmit (Tx) connector.
a.
Attach the other end to the port receive (Rx) connector.
b.
At the circuit source card:
Step 12
Connect the transmit (Tx) connector of the test set to the circuit receive (Rx) connector.
a.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
b.
Verify that the test set displays a clean signal. If a clean signal is not displayed, repeat Steps
Step 13
10
to make sure the test set and cabling are configured correctly.
Inject BIT errors from the test set. To verify that you have a complete end-to-end circuit, verify that the
Step 14
errors display at the test set.
Complete the
Step 15
From the View menu choose Go to Network View.
Step 16
Step 17
Click one of the two spans leaving the circuit source node and complete the
Switching Test" task on page 4-26
Although a service interruption under 60 ms may occur, the test circuit should continue to work before,
during, and after the switches. If the circuit stops working, do not continue. Contact your next level of
support.
In network view, click the other circuit source span and complete the
Step 18
Switching Test" task on page 4-26
Although a service interruption under 60 ms may occur, the test circuit should continue to work before,
during, and after the switches. If the circuit stops working, do not continue. Contact your next level of
support.
Set up and complete a BER Test. Use the existing configuration and follow your site requirements for
Step 19
the length of time. Record the test results and configuration.
Complete the
Step 20
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete. Refer to the
Step 21
Cisco ONS 15327 Troubleshooting Guide.
View the alarms and conditions on each node and record results by exporting them to a file. See the
Step 22
"DLP-B139 Export CTC Data" task on page 6-3
Repeat Steps
Step 23
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails
Step 24
again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for
service application. Continue with
Stop. You have completed this procedure.
March 2003
"DLP-B254 XTC Active/Standby Switch Test" task on page
for instructions.
for instructions.
"NTP-B152 Delete Circuits" procedure on page 8-15
8
through
22
for each node on the network.
Chapter 5, "Create Circuits and VT Tunnels."
NTP-B177 Path Protection Acceptance Test
4-8.
"DLP-B94 Path Protection
for the test circuit.
for instructions.
Cisco ONS 15327 Procedure Guide, R4.0
1
through
"DLP-B94 Path Protection
4-25