Connecting Cables To Power Supply And Distribution Devices - Huawei FusionModule2000 Installation Manual

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Installing Panels
1.
2.
Figure 11-34 Installing filler panels
11.10.2 Connecting Cables to Power Supply and Distribution
Devices
To connect cables to power supply and distribution devices, see the documents delivered with
the devices.
Table 11-3 Reference documents for power supply and distribution devices
Device Name
Industrial connector
(optional)
PDU2000 (optional)
Integrated UPS
Issue 01 (2017-07-30)
Reinstall the circuit breaker panel.
Secure filler panels to the rack rails on the rear door, as shown in
Each filler panel occupies 2 U. Install them according to the U position markings on the cabinet. Ensure
that filler panels fully cover the rack rails.
Table 11-3
lists the reference documents.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Reference
A.6 (Optional) Connecting Cables to Industrial Connectors
A.7 (Optional) Connecting PDU2000 Cables
UPS5000-E-(20 kVA–80 kVA) Quick Guide (Integrated UPS,
208 V)
The document is delivered with the device, or you can click
Download.
11 Cable Routing
Figure
11-34.