FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 3-11 Connecting bases
----End
Result
After securing bases, ensure that adjacent bases are in close contact with each other and the
gap is even.
3.1.2 Installing Fixed-Size Bases
3.1.2.1 Deploying a 300 mm Wide Air Conditioner Base
Context
A 300 mm wide fixed base adapts to a 300 mm wide air conditioner. The BOM number for a
300 mm wide fixed base is 21152146.
Figure 3-12
Issue 01 (2017-07-30)
shows a 300 mm wide fixed base.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
25