FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Step 4 Install remaining cabinets in a similar way.
If there are four cabinets in one row and eight cabinets in both rows, use the laser locator to check the
sides of newly installed cabinets. Ensure that the front-backward misalignment between the two rows of
cabinets is within 1.5 mm, as shown in
Issue 01 (2017-07-30)
Figure 4-9 Interconnecting cabinets
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
4-10. Adjust the cabinet gap if needed.
4 Installing Cabinets
64