Optional) Installing Cable Separation Panels On Control Skylights - Huawei FusionModule2000 Installation Manual

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 5-7 300 mm wide flat skylight
(1) Skylight connective plate
5.1.2 (Optional) Installing Cable Separation Panels on Control
Skylights
Context
Cable separation panels for control skylights are available in control skylight materials.
Procedure
Step 1 Interconnect cable separation panels, as shown by (1) and (2) in
Issue 01 (2017-07-30)
The 300 mm wide flat skylight is used with a 300 mm wide air conditioner.
If no cable trays are deployed, install cable separation panels for control skylights.
If cable trays are deployed, do not install cable separation panels for control skylights.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installing the Contained Aisles
(2) Flat skylight panel
Figure
5-8.
81