Huawei FusionModule2000 Installation Manual page 76

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 4-12 Assembling the top panel
Step 2 Use M4x10 screw assemblies to secure connecting kits to the front and rear panels, as shown
in
Figure
Figure 4-13 Installing connecting kits
Step 3 Clamp the front panel between cabinets and ensure that its front surface is flush with the
cabinet doors. Use connecting kits and M4x10 screw assemblies to connect the front panel to
the adjacent cabinets, as shown in
Issue 01 (2017-07-30)
4-13.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
4-14.
4 Installing Cabinets
67