FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Name, Specifications, and Appearance
Adjustable socket
screwdriver
NOTE
This table may not list some tools required at specific sites. Onsite installation personnel and technical
support personnel should prepare tools based on site requirements.
Table 1-4 Transportation and unpacking tools
Tool Appearance, Specifications, and Name
Pallet truck
Table 1-5 Air conditioner tools
Tool Appearance, Specifications, and Name
Cutter
Oxygen
Issue 01 (2017-07-30)
Flashlight
Diesel forklift
Water pipe thread
a
sealant
Acetylene
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1 Installation Preparations
Clamp meter
Lifting rope (bearing
capacity ≥ 400 kg)
Welding torch
Hot melt device (for
rigid water pipes)
Phase sequence
meter
Lever (bearing
capacity ≥ 400 kg)
5% silver solder
d
Nitrogen