Figure 3-32 Removing packing materials
Step 5 Remove the plastic bag and take out the fittings box and sliding plates.
Step 6 Check that the UPS is intact.
1.
2.
Step 7 After verifying that the UPS is intact, remove the L-shaped brackets securing the cabinet and
pallet, and insert the two sliding plates under the pallet, as shown in
Figure 3-33 Removing the L-shaped bracket
Issue 01 (2017-07-30)
Visually inspect the UPS appearance for shipping damage. If it is damaged, notify the
carrier immediately.
Check that the fittings comply with the packing list. If some fittings are missing or do
not comply with the packing list, record the information and contact your local Huawei
office immediately.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
Figure
3-33.