Figure 11-15 Cable routes for the aisle lighting system
(1) AC actuator
After aisle lights are installed, connect cables by performing the following steps:
Interconnect the male and female connectors of lights in the same group.
For lights in the same group, only the light in either end needs to be connected to the
power supply.
For lights in different groups, power must be supplied to each group separately.
Figure 11-16 Cable connections to lights in the same group
(1) AC actuator
Issue 01 (2017-07-30)
(2) Light
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
11 Cable Routing
(3) Light button