Pay attention to the direction of the magnetic lock fixing plate, and ensure that the protruded
surface of the magnetic lock faces the magnet.
Step 4 Install the magnetic lock. Route cables of the magnetic lock into the upper frame mounting kit,
and secure the magnetic lock to the fixing plate using the hex key delivered with the magnetic
lock, as shown by (2) in
Figure 8-36 Installing a magnetic lock
Step 5 Install the mounting plate of the magnetic lock cover.
Figure 8-37 Installing the mounting plate of the magnetic lock cover
Step 6 Install the magnet.
Issue 01 (2017-07-30)
Figure
8-36.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Installing Monitoring Devices
147

Advertisement

Table of Contents
loading

Table of Contents