FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 6-2 Installing cable ladder supports
Step 2 Insert the cable ladder into the cable ladder supports and adjust the position until the spring
holders are snapped into the holes in the T-shaped brackets.
Figure 6-3 Installing a cable ladder
Step 3 Use a ground cable to connect the ground screws on the cable ladder and its supports.
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 (Optional) Installing Cable Trays