17.7 (Optional) Cable Routing for the Air Conditioner
PDB
Cabling mode for the air conditioner PDB: Cables can be routed in from the top and out from
the top or bottom.
Figure 17-13 Cable routing for the air conditioner PDB
(1) Input power cables for the air conditioner PDB (powered by the
customer's power supply)
17.8 Connecting Cables to the Power Supply and
Distribution System
17.8.1 Connecting Cables to Power Supply and Distribution
Devices
For details, see the document delivered with the equipment or obtain the required document
according to the section "Documentation Preparations."
Issue 02 (2018-03-31)
The figure is for reference only. The actual scenario prevails.
If the power supply system is used in the 2N scenario, BSC cables need to be connected between UPSs.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
17 Connecting Cables
(2) Air
conditioner
278

Advertisement

Table of Contents
loading

Table of Contents