A.4.5.2 Installing Telescopic Edges
Procedure
Step 1 Extend the two telescopic edges to an appropriate length and secure them using two M6 bolts.
Figure A-15 Adjusting the length of a telescopic edge
Step 2 Secure the two telescopic edges to the skylight connective plate using four M6 bolts.
Figure A-16 Installing telescopic edges
(1) Column
Issue 01 (2017-07-30)
(2) Telescopic edges
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(3) Skylight connective plates