Step 2 Install the guide rail and glass doors.
Before installation, remove the protective rubber strips from the glass panel.
1.
Issue 01 (2017-07-30)
Stand the door frame, and partially secure (do not fully tighten the fasteners) left and
right posts to the skylight connective plates using four M6x16 screws, flat washers, and
nuts, as shown by (1) in
Secure the left and right posts to the cabinet using four M6x16 screws, as shown by (2)
in
Figure
5-17.
Before tightening the screws, remove the clips and set them aside to facilitate installation. After
tightening the screws, reinstall the clips on the posts.
Verify that the posts are flush with the cabinet frame.
Measure the levelness of the upper frame mounting kit using a level. If the levelness is
greater than or equal to 0.5° , adjust the cabinet anchor bolts to level the upper frame
mounting kit.
Tighten the four M6x16 screws and nuts to secure the left and right posts to the skylight
connective plates.
Reinstall the post side panels, as shown by (3) in
Figure 5-17 Installing a door frame
Install the glass door rubber strips and magnet fasteners, as shown in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
5-17.
5 Installing the Contained Aisles
Figure
5-17.
Figure
5-18.
90