Placing Precautions
Place the cartons in order based on the carton numbers, as shown in
Figure 1-2 Arranging components

1.2 Unpacking and Acceptance

Context
Unpack and inspect all cabinets, mechanical parts, and components. Check that all the items
are intact and comply with the packing list on the presence of both the project supervisor and
customer.
Procedure
Step 1 Unpack the carton labeled "Contain Packing List" and take out the Packing List.
Step 2 Check all items against the Packing List.
Step 3 If an item is incorrect or missing, contact Huawei technical support.
Step 4 If any item is damaged, fill in the Cargo Replacement Application Form and report it.
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1 Installation Preparations
Figure
1-2.
2

Advertisement

Table of Contents
loading

Table of Contents