Huawei FusionModule2000 Installation Manual page 33

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Procedure
Step 1 Move away the base and install expansion bolts, as shown in
Figure 3-9 Installing an expansion bolt (unit: mm)
Step 2 Measure the hole depths and distances. If any deviation is found, mark the positions again and
drill new holes.
Step 3 Deploy the base again, adjust the base position, and partially tighten the expansion bolts.
Step 4 Measure the levelness of the base using a level, as shown by (1) in
Step 5 If the base is not level, put spacers under it, as shown by (2) in
Step 6 Tighten the four expansion bolts using a torque wrench, as shown by (3) in
Figure 3-10 Leveling the fixed base
Step 7 Secure other bases in the same way.
Step 8 After securing bases, connect bases using connecting plates, as shown by (1) in
and secure the screws to the floor holders on the bases, as shown by (2) in
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
Figure
3-9.
Figure
3-10.
Figure
3-10.
Figure
Figure
Figure
3-11.
3-10.
3-11,
24