FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 5-20 Installing the dampers
Step 4 Install the hanging kits and door boxes, as shown in
For cabinets with different depths, the number of conversion brackets to be installed may differ, but the
installation method is the same. The following uses a 1200 mm deep cabinet as an example to describe
how to install conversion brackets.
Figure 5-21 Installing the hanging kits and door boxes
1.
2.
Issue 01 (2017-07-30)
Snap the middle door box into the upper frame mounting kit. Secure the middle door box
to the door frame using three M4x12 screw assemblies, as shown by (1) in
Facing the aisle, secure the hanging kits marked L and R respectively to the left and
right cabinets using M5x10 tapping screws, as shown by (2) in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installing the Contained Aisles
Figure
5-21.
Figure
5-21.
Figure
5-21.
93