Huawei FusionModule2000 Installation Manual page 139

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Step 3 Secure the ECC800 in the network cabinet by tightening the M6 screws on the left and right
mounting ears clockwise.
Figure 8-10 Installing an ECC800
Step 4 (Optional) Remove the ECC800 main control module and install the SIM card in the correct
slot of the main control module as required.
1.
2.
Issue 01 (2017-07-30)
Loosen the captive screws on both sides of the ECC800 main control module, pull the
handles on both sides of the main control module, and take out the main control module.
Figure 8-11 Removing an ECC800 main control module
Install the SIM card in the correct slot on the left side of the ECC800 main control
module.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.