Figure 8-28 Removing the rear plate from the upper frame mounting kit
Step 2 Install the WiFi converter onto the guide rail. Determine the installation position for the WiFi
converter based on the label on the upper frame mounting kit. Align the upper slot on the rear
mounting kit of the WiFi converter with the upper part of the guide rail and then press the
lower part of the converter to clamp the lower slot of the converter to the guide rail. Shake the
WiFi converter in different directions to check that it is securely installed.
Figure 8-29 Installing the WiFi converter onto the guide rail
(1) Guide rail
Step 3 Install stop blocks. Install two stop blocks on the two sides of the WiFi converter to stop the
movement of the converter.
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Installing Monitoring Devices
142

Advertisement

Table of Contents
loading

Table of Contents