Figure A-18 Installation position of the adjustable skylight side sealing plate
(1) Adjustable skylight side sealing plate
Procedure
Step 1 Trim the PC plate to an appropriate size using a hook knife.
Issue 01 (2017-07-30)
To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the No. 0 packing
box.