Context
If the air conditioner implements cold-aisle control, install the T/H sensor on the door frame
of the IT cabinet front door. If the air conditioner implements hot-aisle control, install the T/H
sensor on the door frame of the IT cabinet rear door.
Procedure
Step 1 Secure the T/H sensor base to the 33 U position on the IT cabinet door frame using M5x10
tapping screws.
Step 2 Mount the T/H sensor onto the base.
Figure 8-69 Installing a T/H sensor
----End
Issue 01 (2017-07-30)
The installation position for the T/H sensor can be adjusted between 33 U and 40 U based on site
requirements.