13.1 Power-On Commissioning Process

Figure 13-1
Figure 13-1 Power-on commissioning process
13.2 Commissioning the Power Supply and Distribution
System
For details about how to commission each device in the power supply and distribution system,
see the documents delivered with it.
Table 13-1 Reference documents for power supply and distribution devices
Device Name
Industrial connector
(optional)
Issue 01 (2017-07-30)
13

Power-On Commissioning

shows the power-on commissioning process.
Reference
A.6 (Optional) Connecting Cables to Industrial Connectors
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Table 13-1
lists the reference documents.
13 Power-On Commissioning