FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 10-1 Installing a cabinet sealing plate
Step 2 Install another sealing plate for the cabinet rear door in the same way.
----End
Installing 300 mm Wide Air Conditioner Sealing Plates
Step 1 Use two M5x10 tapping screws to secure a 300 mm wide air conditioner sealing plate to a
cabinet.
Figure 10-2 Installing 300 mm wide air conditioner sealing plates
Step 2 Install another sealing plate on the other side of the cabinet in the same way.
----End
Issue 01 (2017-07-30)