A.4.2 Installation Process for Scenarios with Columns
Figure A-10 Installation flowchart
A.4.3 Installing a Cabinet Bottom Sealing Plate
Context
The cabinet bottom sealing plate installed in the scenario with a column is the same as the
mounting kit installed under the end cabinet. The BOM number is 21242007.