7.3 Installing an 800 mm Wide Cable Trough

An 800 mm wide cable trough (BOM number: 21501140) is installed on the top of an 800
mm wide cabinet. The installation method is similar to the method for installing a 600 mm
wide cable trough. For details, see

7.4 Installing End Panels for Cable Troughs

Context
Typically, end panels are installed only on cable troughs of cabinets at the two ends of an aisle.
The end panels are marked by different colors to facilitate the identification of power and
signal cables. The red end panel should be installed on the trough for power cables, and the
blue end panel should be installed on the trough for signal cables. Generally, the power cable
trough is located close to the aisle containment, and the signal cable trough is located far away
from the aisle containment.
Procedure
Step 1 Hold the top of the end panel with both hands to keep it vertical. Press it from the top to the
bottom into the hooks at the end of the cable troughs until the top of the end panel is flush
with the top of the cable troughs, as shown in
Issue 01 (2017-07-30)
Obtain the cable trough end panels from the end door materials.
During the installation, the interconnecting wrench is vertical.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 (Optional) Installing Cable Troughs
7.1 Installing a 600 mm Wide Cable
Figure
7-11.
Trough.
122

Advertisement

Table of Contents
loading

Table of Contents