If no pad is configured, skip this step and route the access monitoring cable from the cable hole in the
door box baffle plate.
Figure 8-58 Routing the access monitoring cable (no pad is configured)
Step 5 Tighten two M3 captive screws to secure the baffle plate to the hanging kit.
Figure 8-59 Securing a baffle plate
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.