Huawei FusionModule2000 Installation Manual page 212

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Issue 01 (2017-07-30)
Figure 11-26 Installing a separator
Figure 11-27 Attaching the battery label
Route and secure cables between layers along the rack rail in the vertical direction, as
shown by (1) in
Figure
11-28.
Route and secure cables between layers along the tray supporting beam in the horizontal
direction, as shown by (2) in
Figure 11-28 Cable routes
(Optional) When battery cabinets are installed adjacent to each other, remove the upper
side plates from the battery cabinets for routing cables to the corresponding ports.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
11-28.
11 Cable Routing
203

Advertisement

Table of Contents
loading