Securing Skylights - Huawei FusionModule2000 Installation Manual

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 5-8 Installing cable separation panels
Step 2 Use four M5x10 tapping screws to secure the cable separation panels to the control skylight
panel, as shown by (3) in
----End

5.1.3 Securing Skylights

Context
Install skylights one by one from one end of the smart module based on the onsite engineering
layout diagram.
The recommended skylight layout is as follows:
Procedure
Step 1 Keep the skylight connective plates flush with the end plane of the cabinet upper sealing plate
in the aisle containment. Use four M8x20 screws to partially secure the two skylight
connective plates to the correct mounting holes, as shown by (1) in
Issue 01 (2017-07-30)
Figure
Install control skylights at the outermost positions at both ends of the aisle.
Deploy rotating skylights and flat skylights alternately.
Preferentially deploy rotating skylights beside control skylights.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5-8.
5 Installing the Contained Aisles
Figure
5-9.
82