4.2 Unpacking the Chassis

Step 1 Check that the packaging is in good condition.
Step 2
Be careful with the box cutter to avoid personal injury or equipment damage.
Cut open the pressure-sensitive adhesive tape on the package, and open the box.
Step 3 Check the contents against
free from oxidation, corrosion, or damage.
Table 4-2 Shipped items
No.
1
2
3
----End

4.3 Installing Optional Parts

Before installing and configuring the server, you need to install all optional parts required, for
example, extra CPUs, drives, and PCIe cards. For details, see

4.4 Installing the Server on Guide Rails

4.4.1 Installing with L-Shaped Guide Rails

L-shaped guide rails are designed for Huawei cabinets.
The 2288H V5 servers are stackable when L-shaped guide rails are used.
Step 1 Install the floating nuts.
Issue 04 (2018-09-04)
Air filters installed on cabinet doors.
AC power supplied from the rear of the cabinet.
NOTE
If there is damage (for example, if the package is soaked or deformed, or the seals or pressure-sensitive
adhesive tapes are not intact), submit the Cargo Problem Feedback Form.
CAUTION
Description
Documentation bag that contains a warranty card, and a Quick Start Guide
Guide rails
Rack server
Copyright © Huawei Technologies Co., Ltd.
Table 4-2
to ensure that nothing is missing. Check that they are
5 Optional Part
Installation.
4 Setup
69

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r005

Table of Contents