Installing the ONS 15454 M2 Shelf
Step 7
If the LCD shows the correct software version, continue with the next step. If the LCD does not show the
correct software version, refer to your next level of technical support, upgrade the software, or remove the
TNC/TNCE/TSC/TSCE card and install a replacement card. Refer to the release-specific software upgrade
document to replace the software.
Step 8
(ONS 15454 M6 shelf only) Repeat Steps 1 through 7 for the redundant
TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O card.
Tip
Step 9
Return to your originating procedure (NTP).

DLP-G605 Provision PPM and Port for the TNC and TNCE Cards

Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Procedure
Step 1
In node view (single-shelf mode) or shelf view (multishelf view), double-click the TNC and TNCE cards
where you want to provision PPM and port settings.
Step 2
Click the Provisioning > Pluggable Port Modules tabs.
Step 3
In the Pluggable Port Modules area, click Create. The Create PPM dialog box appears.
Step 4
In the Create PPM dialog box, complete the following:
• PPM—Choose 1 or 2 from the PPM drop-down list.
• PPM Type—Displays the PPM associated with the chosen PPM in the above step.
Step 5
Click OK. The newly created PPM appears in the Pluggable Port Modules area. The row in the Pluggable
Port Modules area becomes white when the PPM is inserted and the Actual Equipment Type column lists the
name of PPM.
If you install a standby TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O card that has a different software
version than the active TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O card, the standby
TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O card copies the software version from the active
TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O card. When the standby card is first inserted, the LEDs
follow the normal boot-up sequence. However, after the red FAIL LED turns on for about 5 seconds,
the FAIL LED and the ACT/STBY LED begin to flash alternately for up to 30 minutes. After loading
the new software, the upgraded TNC/TNCE/TSC/TSCE/TNCS-2/TNCS-2O cards LEDs repeat the
appropriate bootup sequence, and the amber ACT/STBY LED turns on.
(ONS 15454 M2 and ONS 15454 M6 only) This task provisions a PPM and port
on a TNC and TNCE cards. PPMs are created to support the OSC function.
None
DLP-G46 Log into CTC
As needed
Onsite or remote
None
DLP-G605 Provision PPM and Port for the TNC and TNCE Cards