Dlp-G599 Turn On And Verify Ac Office Power On The Ons 15454 M2 Shelf - Cisco ONS 15454 Hardware Installation Manual

Hide thumbs Also See for ONS 15454:
Table of Contents

Advertisement

Installing the ONS 15454 M2 Shelf
Step 3
Attach the DC ETSI power cables to the DSUB power connectors of the DC power module (see the following
figure).
Step 4
Tighten the screws to a torque value of 4 in-lb (0.45 N-m) to secure the cable.
Figure 167: Connecting Office Power—DC Power Module (ETSI Only)
Note
Caution
Caution
Step 5
Return to your originating procedure (NTP).

DLP-G599 Turn On and Verify AC Office Power on the ONS 15454 M2 Shelf

Purpose
Tools/Equipment
Use only pressure terminal connectors, such as ring and fork types, when terminating the battery,
battery return, and frame ground conductors.
Before you make any crimp connections, coat all bare conductors (battery, battery return, and frame
ground) with an appropriate antioxidant compound. Bring all unplated connectors, braided strap,
and bus bars to a bright finish, then coat with an antioxidant before you connect them. You do not
need to prepare tinned, solder-plated, or silver-plated connectors and other plated connection surfaces,
but always keep them clean and free of contaminants.
When terminating power, return, and frame ground, do not use soldering lug, screwless (push-in)
connectors, quick-connect, or other friction-fit connectors.
This task measures the power to verify correct power and returns for the ONS
15454 M2 shelf.
Voltmeter
DLP-G599 Turn On and Verify AC Office Power on the ONS 15454 M2 Shelf
Cisco ONS 15454 Hardware Installation Guide
251