Installing the ONS 15454 M12 (ANSI and ETSI) Shelf
Description
NTP-G13 Install the Rear Cover (ANSI Only), on page 118
NTP-G14 Install DWDM Equipment, on page 123
NTP-G15 Install the Common Control Cards, on page 131
NTP-G301 Connect the ONS 15454 Multishelf Node and Subtending Shelves to an MS-ISC-100T
Card, on page 138
Shelves to a Catalyst 2950 or Catalyst 3560, on page 146
NTP-G298 Configure a Cisco Catalyst 2950 or Catalyst 3560 (Active and Standby) for a ONS
15454 Multishelf Node, on page 152
Multishelf Node and Subtending Shelves to a Catalyst 2950 or Catalyst 3560, on page
Step 3
Complete the
Step 4
Complete the
Step 5
Continue with "
Stop. You have completed this procedure.

DLP-G35 Inspect the Shelf Installation and Connections

Purpose
Tools/Equipment
Prerequisite
Procedures
Required/As Needed
Onsite/Remote
Security Level
Procedure
Step 1
Make sure all external wiring connections on the backplane (that is, power, ground, alarms, etc.) are secure.
If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it.
Step 2
(ETSI only) To check that the FMEC cover is seated correctly, verify that it can be easily closed without
disturbing cables.
Step 3
Return to your originating procedure (NTP).
or
NTP-G295 Connect the ONS 15454 Multishelf Node and Subtending
(if you completed
DLP-G35 Inspect the Shelf Installation and Connections , on page
DLP-G36 Measure Voltage , on page
Connect the PC and Log into the GUI
Use this task to inspect the shelf installation and connections and verify that
everything is installed and connected properly.
None
None
Required
Onsite
None
DLP-G35 Inspect the Shelf Installation and Connections
NTP-G295 Connect the ONS 15454
146.
" document.
Cisco ONS 15454 Hardware Installation Guide
Completed
146)
145.
145

Advertisement

Table of Contents
loading

Table of Contents