Installing the ONS 15454 M2 Shelf
Step 2
Click the Provisioning > UDC / VOIP tabs.
Step 3
From the Service Type drop-drop list, choose UDC or VOIP.
Note
Step 4
Click Apply.
Step 5
Return to your originating procedure (NTP).
NTP-G275 Perform the ONS 15454 M2 Shelf Installation Acceptance Test
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Procedure
Step 1
If you installed an ONS 15454 M2 shelf, complete the following table by verifying that each applicable
procedure was completed.
Table 31: ONS 15454 M2 ETSI Shelf Installation Task Summary
Description
NTP-G305 Unpack and Inspect the ONS 15454, ONS 15454 M2, and ONS 15454 M6 Shelves,
on page 20
NTP-G266 Install the ONS 15454 M2 Shelf, on page 194
Connect the chassis to the office ground. For detailed instructions on how to ground the chassis,
refer to the
.
NTP-G270 Open and Remove the Standard Door of the ONS 15454 M2 Shelf, on page 218
NTP-G267 Install the Power Module in the ONS 15454 M2 Shelf, on page 230
NTP-G271 Install the Power and Ground to the ONS 15454 M2 Shelf, on page 239
NTP-G268 Install the Fan-Tray Assembly in the ONS 15454 M2 Shelf, on page 235
You can configure UDC or VoIP on only one SFP port at a time per TNC and TNCE cards. If you
want to configure UDC or VoIP on the second SFP port, choose NONE from the Service Type
drop-down list for the first port and then choose UDC or VoIP for the second port.
Use this procedure to perform a shelf installation acceptance test for the ONS
15454 M2.
Voltmeter
Applicable procedures in
Required
Onsite
None
Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms
NTP-G275 Perform the ONS 15454 M2 Shelf Installation Acceptance Test
Installing the ONS 15454 M2 Shelf, on page 177
Cisco ONS 15454 Hardware Installation Guide
Completed
267