This topic describes how to configure 1:1 linear MSP services in an end-to-end manner.
Prerequisite
l
l
l
l
Procedure
Step 1 Choose Service > SDH Trail > Create SDH Trail from the Main Menu.
Step 2 Create the VC-4 service-layer trail.
1.
2.
3.
Step 3 Create VC12 services.
1.
2.
3.
Issue 02 (2011-06-30)
The physical network topology must be set up.
NEs, boards, and fibers must be successfully created on the U2000.
A linear MSP subnet must be created and must be the same as the actual topology. For
details about how to create a protection subnet, see
Subnet.
The operator must understand the information provided in
Allocation.
Configure the parameters as follows. Set Level to VC4 Server Trail. The other parameters
take default values.
Double-click the source NE (NE1) and sink NE (NE2) on the right of the main topology
and click Apply. In the Operation Result dialog box indicating that the operation
succeeded, click Close.
Optional: In the Operation Result dialog box indicating that the operation succeeded,
click Browse Trail to query the created VC4 service-layer trail.
In Create SDH Trail, configure the parameters as follows. Set Level to VC12. The other
parameters take default values.
Double-click the source NE (NE1) on the right of the main topology. The Select Board
Port-Source dialog box is displayed. Select the required SP3D board and Tributary
Port. Click OK.
Double-click the sink NE (NE2) on the right of the main topology. Configure NE2 in the
same manner.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Configuring SDH Services
2.6.4 Creating a Linear MS Protection
3.5.2 Signal Flow and Timeslot
3-25

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents