Commissioning An Emergency Door Release Button; Video Management; Reference Documentation; Networking Scenarios - Huawei SmartDC V100R021C10 User Manual

Data center controller
Hide thumbs Also See for SmartDC V100R021C10:
Table of Contents

Advertisement

ECC800 Data Center Controller
User Manual

6.4.4 Commissioning an Emergency Door Release Button

Procedure
Step 1 Check the function of an emergency door release button.
Table 6-18 Function commissioning
Check Method
When the room door is
properly closed, short-
circuit the wiring
terminals NC and COM
or NO and COM on the
emergency door release
button.
----End

6.5 Video Management

6.5.1 Reference Documentation

Before commissioning a camera, prepare the following documents in addition to
this document.
Table 6-19 Documentation for commissioning
Component
IPC6325-WD-VR
C3220
VCN500/VCN510/
VCN520/VCN540
IVS1800

6.5.2 Networking Scenarios

Smart ETH Gateway Networking Scenario
Issue 04 (2021-10-09)
If there are multiple VCNs or IVS1800s for multiple smart modules, you are
advised to evenly distribute the cameras to each VCN or IVS1800.
Copyright © Huawei Technologies Co., Ltd.
Normal Connection
Status
The room door is opened
properly.
Document
IPC6325-WD-VR Configuration Guide
Huawei C Series SDC 8.0.1 Product Documentation
VCN500: VCN500 Product Documentation
VCN510/VCN520/VCN540:
VCN510&VCN520&VCN540 Product Documentation
IVS1800 8.1.0 Product Documentation
6 Feature Description
Follow-up Procedure
Remove the short-circuit
cable from the wiring
terminals NC and COM
or NO and COM on the
emergency door release
button.
145