4.
Step 4 If there are multiple eLights, repeat
----End
5.8 Commissioning the PDU2000 (for
FusionModule500/800)
When the system type is FusionModule500/800 and a PDU2000 is installed,
perform the following steps to configure it.
Issue 04 (2021-10-09)
Table 5-13 Function commissioning
Item
Associated
alarm severity
NOTE
After you set the alarm severity, the eLight indicator is off if no alarm is generated.
(Optional) When the eLight is connected to a cabinet, commission the cabinet
light.
When you open the front door of the cabinet, the tube light connected at
the front door turns white.
When you open the rear door of the cabinet, the tube light connected at
the rear door turns white.
When the front or rear door of the cabinet is closed, the corresponding
light color is displayed based on the setting of Associated alarm
severity.
Copyright © Huawei Technologies Co., Ltd.
Alarm Severity
Selection
Critical
Critical, Major
Critical, Major,
Minor
Critical, Major,
Minor, Warning
None
Step 1–Step
5 Power-On Commissioning
Description
If there is a critical alarm, the
eLight strip light turns on with a
red light.
If there are multiple alarms, the
eLight strip light preferentially
turns on with a light
corresponding to the high-
severity alarm. After the high-
severity alarm is cleared, the
eLight strip light turns on with a
light corresponding to the low-
severity alarm.
NOTE
– Critical: red light
– Major: orange light
– Minor: yellow light
– Warning: gray light
The eLight strip light is steady
blue (atmosphere light).