6.8.1 Configuring PUE Standard Mode

Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
Step 2 Choose System Settings > PUE Configuration.
Step 3 Set PUE function to Enable.
Step 4 Set PUE configuration mode to Standard, and click Submit.
Step 5 View the PUE. Choose Query > Performance Data and set Device to ECC800
from the drop-down list box. For other searching criteria such as Performance
data, Statistics mode, Start time, and End time, select the item based on
requirements and click Query. You can also view the PUE in the dashboard or
curve on the home page.
----End
Example of PUE Calculation
In this example, the PUE is calculated on the basis of the start time 17:00 and end
time 18:00.
1.
2.
3.
Issue 04 (2021-10-09)
Choose Query > Performance Data.
Set Device to ECC800, Performance data to Total system input electrical
energy, and Statistics Mode to Hour, set other query criteria such as Start
time and End Time as required, and click Query. Record the increment in
total system input electrical energy of the ECC800-Pro. Increment in total
system input electrical energy = 110.0 kWh – 100.0 kWh = 10.0 kWh.
Figure 6-85 Querying the total system input electrical energy
Set Device to ECC800, Performance data to Total electrical energy of
system IT load output, and Statistics mode to Hour, set other query criteria
such as Start time and End time as required, and click Query. Record the
increment in total electrical energy of system IT load output of the ECC800-
Pro. Increment in total electrical energy of system IT load output = 56.0 kWh
– 50.0 kWh = 6.0 kWh.
Copyright © Huawei Technologies Co., Ltd.
6 Feature Description
236

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ecc800

Table of Contents