Commissioning Configuration Wizard - Huawei SmartDC V100R021C10 User Manual

Data center controller
Hide thumbs Also See for SmartDC V100R021C10:
Table of Contents

Advertisement

ECC800 Data Center Controller
User Manual
----End

5.3 Commissioning Configuration Wizard

Context
Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
The configuration wizard is displayed when you log in to the ECC800-Pro WebUI for the first
time or the system type is switched.
Step 2 Choose Maintenance > Configuration Wizard to access the parameter
configuring page for the deployment wizard.
Step 3 Configure related parameters on the page as instructed. For details, see the
function description on the left of the page.
Step 4 After configuring the parameters, click Finish.
Step 5 After confirming that the commissioning Result is normal, enter the Checker
Name and Check Date, and click Configuration Completed.
Issue 04 (2021-10-09)
b.
If the message displayed on the page is changed from "Initial startup
password authentication" to "Activated", the startup password
authentication is complete.
NO TE
– After the first login, change the password in time to ensure system access security.
– A password that has been used for a long time is more likely to be stolen or cracked.
The risk increases along with the time of use. Change the password once three months.
– It is recommended that you use different user names to log in to both the ECC800-Pro
WebUI and app at the same time. If you use the same user name to log in to the
WebUI and app at the same time, either of them will be forcibly logged out.
– The iDCService app supports only the Android system.
– The iDCService app is available only in Chinese.
Only administrators are entitled to perform the configuration wizard.
Currently, commissioning wizard is provided for the following functions:
Smart Module Settings, Basic Param Settings, Add Devices, Add Sensor,
Plan View, Power Dist Settings, Temp Control Settings, Linkage Test,
Video Settings, and Access Management.
NO TE
NO TE
● In the process, click Previous, Next, and Skip as required.
● To exit before the configuration is complete, click Finish to terminate the configuration
directly.
Copyright © Huawei Technologies Co., Ltd.
5 Power-On Commissioning
105