User Manual
Prerequisites
Context
After installing or replacing the device or ECC800-Pro, set monitoring parameters
and add the device.

5.1 Preparations and WebUI Login

Prerequisites
Procedure
Step 1 Connect a network cable between the PC network port and the WAN1 port
(protected by a security mechanism) on the ECC800-Pro.
Table 5-1 Default IP addresses for the WAN and LAN ports on the ECC800-Pro
Port
WAN1
Issue 04 (2021-10-09)
5
The hardware and cable installation check is complete for controller
components according to data center specifications and requirements.
The device and ECC800-Pro have been powered on.
You have obtained the ECC800-Pro IP address as well as the user name and
password used for WebUI login.
A PC with an IP address in the same network segment as the ECC800-Pro IP
address is prepared, and the PC has connected to the WAN1 port on the
ECC800-Pro.
Supported operating system: Windows 7 and later versions
It is recommended that the screen resolution be 1366 x 768 or higher.
Browser: Chrome, Firefox 32, Internet Explorer 11 or later
Copyright © Huawei Technologies Co., Ltd.

Power-On Commissioning

Default IP Address
192.168.8.10
5 Power-On Commissioning