6.6.1.2 High Temperature Linkage

Context
Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
Step 2 Choose System Settings > Linkage Control.
Issue 04 (2021-10-09)
NO TE
After the corresponding AI/DI device is enabled, the AI/DI device type must be
consistent with the DO state.
Table 6-39 Fire sensor NO and NC definitions
Item
NO
NC
Click Submit.
Close the skylight manually.
Start the smart cooling products manually.
After turning off the lights, set Set light mode of the AC actuator to
Automatic. WebUI path: Monitoring > Aisle > AC Actuator Group > AC
Actuator > Running Parameters.
NO TE
When a smart module actuator is configured, you need to set parameters for the
smart module actuator. The setting process is similar.
The ECC800-Pro implements high temperature linkage. If it detects high
temperature alarms by interacting with multi-functional sensors and all smart
cooling products fail to communicate with the ECC800-Pro, the ECC800-Pro
opens skylights based on the alarm status to facilitate heat dissipation.
The default status of high temperature linkage is off. Set it based on the
actual situation.
Copyright © Huawei Technologies Co., Ltd.
6 Feature Description
Definition
Dry contact signal for the fire sensor
abnormality alarm. Closed: alarm;
open: normal
Dry contact signal for the fire sensor
abnormality alarm. Closed: normal;
open: alarm