FusionModule2000 Smart Modular Data Center
Installation Guide
Prerequisites
If there are bases, the bases are leveled and cabinets are placed on the bases.
Preparations
Tools: adjustable wrench, level, Phillips screwdriver
Document: cabinet layout diagram
Procedure
Step 1 (Optional) Partially secure the cabinets to the bases.
1.
2.
Issue 02 (2018-03-31)
If bases are required, perform this step for the PDC, network cabinet, IT cabinet, 600 mm wide air
conditioner, and 300 mm wide M-type air conditioner with feet.
If bases are required, go to
Align the mounting holes on the cabinet with those on the base.
Insert M12x80 screw assemblies into the mounting holes for the cabinet and base, and
partially tighten the screws.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8

Combining Cabinets

Step 3
for cabinets without feet.
8 Combining Cabinets
83