Huawei FusionModule2000 Installation Manual page 280

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide
3.
4.
Issue 02 (2018-03-31)
Figure 17-6 Cutting off the excess part of a cable tie
Do not use cable ties at a place where the cables are bent. Otherwise, the cable cores may
break due to strong stress, as shown in
Figure 17-7 Binding cables in a bending area
Ensure that the cable ties are wrapped and secured in the same direction and do not
generate interference with subsequent operations, as shown in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
17-7.
Figure
17 Connecting Cables
17-8.
271