Step 3 Install the other vertical plate into the mounting hole in the second row counting from the
front door to the rear door in the same way. Install one M5x10 tapping screw inside either of
the two vertical plates to ensure equipotential bonding with the cabinet.
Figure 11-5 Installing the other vertical plate
Step 4 Press a tray along the two vertical plates down to the place between the four clasps and the
cable bridge. Ensure that the tray is fully into the clasps.
When installing the tray, do not remove the grommet strip on the U-shaped trough.
Figure 11-6 Installing a tray
Step 5 Install a partition plate. Press both sides of the V-shaped partition plate with both hands to
decrease the angle to a proper degree, and clamp the clasps at the bottom into the nearby
holes.
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
11 Installing Cable Troughs and Cable Trays
154

Advertisement

Table of Contents
loading

Table of Contents