Ensure that strong-current cables and weak-current cables are at least 100 mm away from
each other.
Connect the power cables from the general input unit side to the smart module.
Figure 17-11 Routing power cables and network cables
(1) General input unit
(4) Power cable
Issue 02 (2018-03-31)
(2) Power distribution unit
(5) Conversion unit